欧美日韩艺术电影在线|霹雳娇娃在线观看完整版免费高清|国产精品电影在线观看|黄色你懂的,边做饭边被躁我和邻居日本 ,南方恶魔未删减版,91欧美在线

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

When a project manager approaches the end of their company’s big project, the company’s organizational structure, objective and Strategies have changed. What should the project manager take from the following methods?
A、Speak with the line one manager to ensure the whole resources should continue to complete the task which assigned before.
B、Check if there is budget available to continue the project following the master schedule.
C、Disregard the change in goals and strategies and continue to run the end.
D、Inquire with the project sponsor as to whether or not the project still fits the company’s Strategies.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容