欧美日韩艺术电影在线|霹雳娇娃在线观看完整版免费高清|国产精品电影在线观看|黄色你懂的,边做饭边被躁我和邻居日本 ,南方恶魔未删减版,91欧美在线

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(5)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The installation project has a CPI of 1.03 and an SPI of 1.0. There are 14 team members and each team member had input into the final project management plan. The customer has accepted the three deliverable completed so far without complaint and the responsibility assignment matrix has not changed since the project began. The project is being completed in a matrix environment and there are no contracts needed for the project. Though the sponsor is happy with the status of the project, one of the team members is always complaining about how much time his project work is taking. Which of the following would be the BEST thing for the project manager to do?
A、Review the reward system for the project.
B、Try to improve schedule performance of the project.
C、Meet with the customer to try to extend the schedule.
D、Gain formal acceptance in writing from the customer.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容