欧美日韩艺术电影在线|霹雳娇娃在线观看完整版免费高清|国产精品电影在线观看|黄色你懂的,边做饭边被躁我和邻居日本 ,南方恶魔未删减版,91欧美在线

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During an informal conversation with a project team member,the project manager discovers that a supplier for a key part has problems implementing an approved product change. Which of the following should the project manager do next ?
A、Perform a quality audit of the supplier.
B、Schedule a change control meeting.
C、Measure the supplier’s work performance.
D、Speak with a senior manager of the supplier.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容