欧美日韩艺术电影在线|霹雳娇娃在线观看完整版免费高清|国产精品电影在线观看|黄色你懂的,边做饭边被躁我和邻居日本 ,南方恶魔未删减版,91欧美在线

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Four months into a 10-month project, the project manager realizes that the project is behind schedule and slippage will lead to an overrun of 25% of the project’s budget. A change request is created, but when the project manager seeks approval, the executive is reluctant to do so. What could be the reason for this executive’s reluctance ?
A、Lack of the project management plan approval.
B、 Lack of the risk management plan approval.
C、 Lack of the communications management plan approval.
D、 Lack of the change management plan approval.


相關(guān)試題

推薦文章